Oilex Ltd has completed plug milling operations. Cambay-77H started unaided controlled flowback with gas observed at surface while successfully milling out 4 isolation plugs, including 1 that failed to seal properly.
Since the previous update on 7 July 2014:
The isolation plugs were successfully milled
8 fractures into the reservoir were connected to the well bore
The well started to flowback unaided under controlled conditions during milling
Gas flowed to surface during milling operations
Production testing equipment was positioned and commissioned