Suncor Energy has completed maintenance work at its oil sands upgrading facilities and production has now returned to full rates.
The maintenance work involved repairs following a fire in February at one of two oil sands upgraders (U1) operated by Suncor near Fort McMurray, Alberta.
Oil sands production during the repair period in March averaged approximately 245,000 barrels per day (bpd). Year-to-date oil sands production at the end of March averaged approximately 202,000 bpd.
Production numbers include upgraded sweet and sour synthetic crude oil and diesel, as well as non-upgraded bitumen sold directly to the market, from all Suncor-operated facilities. Reported volumes do not include Suncor's proportionate production share from the Syncrude joint venture.
Tags:
Suncor Energy
Add a Comment to this Article
Please be civil. Job and promotion will not be added into the comment page.