InterMoor worker gets a riser ready for disconnection
InterMoor, an Acteon company, has successfully completed offshore operations for the disconnection and laydown of risers and mooring lines on a major floating production, storage and offloading (FPSO) facility offshore Angola. InterMoor won the contract in March 2014 and completed the work on budget, on schedule and with zero incidents in Dec. 2014.
The project had two phases: Phase 1 concluded with the disconnection of all 20 risers and umbilicals from the FPSO facility and their placement on the seabed in accordance with the laydown agreement; in Phase 2, InterMoor disconnected all 12 mooring lines and placed them on the seabed while the FPSO was held in place by station-keeping vessels. InterMoor provided the station-keeping procedure and Tow Masters onboard the FPSO.
The initial contract scope included project management, engineering and offshore execution. InterMoor devised multiple methods for disconnection, including the use of clamps to take the load off the risers using the offshore construction vessel (OCV) and either disconnecting or cutting the hang off on the FPSO to lower the risers. The subsea riser clamp design and fabrication were added to the contract once the project progressed. The clamps were designed by Houston-based Acteon company, 2H Offshore, and fabricated in InterMoor’s facility in Morgan City, Louisiana.
João Ruiz, project manager, InterMoor, said, “The successful completion of this project underlines our global reach and demonstrates the specific skills we provide for operations offshore West Africa. InterMoor was selected as the ideal candidate for the project because of our leading position as a mooring, foundations and subsea services provider for rig moves and mooring services, our decommissioning experience and our ability to provide local support from our operations base in Angola.”
Tags:
InterMoor Inc.
Comments on this page are closed.