Sembcorp Marine subsidiary SMOE Pte Ltd has secured an Engineering, Procurement and Construction (EPC) contract worth over USD One billion (including long lead items) from Maersk Oil North Sea UK Limited.
The contract includes the building of the Central Processing Facility plus 2 connecting bridges, Wellhead Platform and Utilities & Living Quarters Platform Topsides for the Culzean Field Development. The facility will be installed at a water depth of some 90 meters in UK sector of the Central North Sea.
SMOE will provide engineering, procurement, construction and onshore pre-commissioning services while detailed engineering work will be performed by a subcontracting partner. The facility will be located in the Culzean field situated 145 miles East of Aberdeen. The project is a high pressure, high temperature (HP/HT) gas condensate development.