The 4.5 inch production liner has been run and cemented into place. Frontier Rig 24 was released Dec 25th to move to the Rennerfeldt 2-13-H well pad.
Frac operations in the Blackdog well are expected to take place following fracture stimulation of the Little Creature 3-15-14HBK well.
Rennerfeldt 2-13-H (SSN WI 25.03%)
Frontier Rig 24 is currently 50% rigged up on the E. Rennerfeldt 2-13-H well pad. The Rennerfeldt well is expected to be spud within the next week.
Little Creature 3-15-14HBK (SSN WI 27.7%)
The Little Creature well has been prepared for frac operations, which were expected to commence December 27th, but due to harsh winter weather conditions frac operations were delayed a few days. The fracture stimulation is expected to begin this morning.