During the course of last week, Frontier Rig 24 successfully set and cemented the 9 5/8 inch surface casing at 2,270 feet on the Coopers 2-15-14HBK. The rig was then skidded to Tooheys 2-15-14HBK and the well spudded on Aug 24th and was drilled to 2,280 feet where the 9 5/8 inch surface casing was set and cemented.
Having set surface casing on both wells, the wells will be drilled sequentially to set the 7 inch casing at around 11,600 feet prior to drilling the 6,200 foot lateral in the middle member of the Bakken Formation.
Sail and Anchor 1-13-14HBK well (SSN WI 25.026%)
The fracture stimulation of the Sail and Anchor well is expected to commence September 9th.