PRD Energy Inc. provided an operational update for the drilling of the Boerger 7A well.
After setting a whipstock at 660m, PRD encountered directional drilling challenges in soft sediments requiring changes to the well plan. The decision has now been made to mill the existing casing, set the whipstock point at approximately 1,200m and then drill to a depth of approximately 2,024m followed by a 400m horizontal leg. Operations to remove the existing whipstock will commence the week of September 16 whereafter plans to complete the balance of the program will be finalized.