Scandoil  

PetroNeft Resources provides operations update


Published Jan 6, 2011
[an error occurred while processing this directive]

Edit page New page Hide edit links

PetroNeft Resources provides operational update-Spotlight

PetroNeft Resources plc, owner and operator of Licences 61 and 67, Tomsk Oblast, Russian Federation, provides an update on its operations at Licence 61.

Highlights: • Year-end production reaches 2,750 bopd from 9 of 11 wells • Fracture stimulation programme to start mid-January 2011 will significantly increase output • Retaining 2011 and 2012 production targets • Lineynoye development programme on schedule; drilling from Pad 2 to start in February • Very good test results for Arbuzovskaya No. 1 well • Third Exploration well added to 2011 drilling schedule • Drilling Contracts awarded for 20 well Exploration and Development drilling programme

Production Year-end production reached 2,750 bopd from 9 of 11 wells drilled. While the performance of the wells is good, production growth is being constrained by greater than expected formation damage resulting from the drilling and completion process. This issue will be overcome by the planned fracture stimulation programme.

Production from the Lineynoye No. 1 well, which is one of the best wells in the field, is not included in the year end production total as the well is currently shut-in awaiting installation of a special screw pump. Also, well 117 was taken offline pre year-end in preparation for fracture stimulation. The current production capacity of the field is estimated at over 3,000 bopd which is less than our year-end target of 4,000 bopd.

The winter fracture stimulation programme will commence in mid-January and the Board are confident that this will significantly increase the well rates by fracing through the near well bore damage and creating additional permeability conduits in the reservoir.

The Board have not changed their view on the overall productivity of the field or long term production targets as our plans have always been to fracture stimulate the wells. Consequently the Board remain confident of achieving the production targets of 8,000 bopd by end 2011 and 12,000 bopd by end 2012.

2011 Licence 61 Development programme - Lineynoye oil field The production drilling rig that drilled the Pad 1 wells will be mobilised to Pad 2 in the coming weeks and drilling of the first of nine wells at Pad 2 should commence by the end of February. A second production drilling rig is being mobilised to Pad 3 where drilling of the first of eight wells will commence in April.

Works to tie-in Pads 2 and 3 to the existing central processing facility have already commenced and it is expected these will be completed by June 2011 thereby allowing new wells to be brought swiftly into production. We are also planning to undertake an early fracture stimulation programme in June 2011 on up to 6 wells from Pads 2 and 3.

Arbuzovskaya Exploration Well The well was drilled to a total depth of 2,903 m on 13 November 2010. The final log data indicates that the base of the Bazhenov Formation is at 2,565 m and is underlain by 5.1 m of good quality oil saturated reservoir in the J1-1 interval. An open hole test of this interval produced at a prorated inflow of 289 bopd. The oil is very high quality with an API gravity of 47.5 degrees. There were no other zones with hydrocarbon indications in the well.

Production casing was run in the well and a step rate DST was performed. Stabilised flow on an 8 mm choke was 176 bopd and the calculated productivity index indicates the well should produce around 400 bopd on pump without fracture stimulation. These are very good results and plans are underway to register the reserves and obtain a pilot production licence which will allow us to tie-in this new field to the Lineynoye central processing facility in 2012.

Ryder Scott is currently assessing the proved and probable reserves for the field. PetroNeft estimates the 2P reserves to be in the 10 to 15 million barrel range. It is expected that the Ryder Scott report will be published in early March 2011.

North Varyakhskaya Prospect Based on the highly encouraging results of the Arbuzovskaya No. 1 well tests, which de-risks the surrounding area, the Board has approved the addition of the nearby North Varyakhskaya No. 1 exploration well to the 2011 drilling programme. If successful, this prospect, which is located 6 km north of Arbuzovskoye oil field, can easily be tied-in to the future Lineynoye to Arbuzovskoye pipeline and could be on production in 2012.

Drilling Tender Results - 2011 Development and Exploration drilling PetroNeft plans to drill a total of 20 wells in Licence 61 during 2011. The programme will consist of two production rigs which will drill 17 development wells from two new pads at Lineynoye and three exploration rigs which will drill the Kondrashevskaya No. 2, North Varyakhskaya No. 1 and Sibkravevskaya No. 372 wells.

Based on drilling tender results the Board has approved the award of the 2011 Drilling Contracts to LLC 'Tomskburneftegaz' (TBNG). TBNG is one of the largest drilling contractors in the Tomsk region. In accordance with AIM Rule 13 and ESM Rule 13, the drilling contracts are deemed to be a related party transaction as Vakha Sobraliev, a Non-Executive director of the Company, is principal owner of TBNG.

Tags: PetroNeft Resources plc




Advertisment:

Add a Comment to this Article

Please be civil. Job and promotion will not be added into the comment page.

(Use Markdown for formatting.)

This question helps prevent spam:

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us

 

sitemap xml