PetroNeft begins production in licence 61, Tomsk Oblast


Published Aug 25, 2010
[an error occurred while processing this directive]

Edit page New page Hide edit links

PetroNeft Resources provides operational update-Spotlight

PetroNeft Resources, owner and operator of Licences 61 and 67, Tomsk Oblast, Russian Federation, provides an update on its operations at Licence 61.

Highlights: • Year-round production commenced on Licence 61 in Tomsk Oblast • Production of 4,000 bopd expected by end 2010 • Seventh production well encounters thickest net oil pay to date

First Oil Construction of production facilities has been completed and production has gradually been commenced from four wells. Field production has been 1,100 bbls of oil in the first two days of production and flow rates are expected to increase as drilling fluids are cleared out and the electric submersible pumps are optimised. Three additional wells will be brought on production over the coming week.

Eleven wells are scheduled to be on production at the end of the year and PetroNeft anticipate meeting their year-end production target of 4,000 bopd. In January 2011, when a crew can be mobilised on winter roads, a programme of hydraulic fracture stimulation will commence in order to achieve the maximum production levels and enhance oil recovery.

Current oil production is being used to complete the commissioning of the oil processing facilities and is filling the oil storage tanks at the facilities site and will commence filling the 60 km pipeline to the Kiev-Eganskoye transfer point shortly.

Development Drilling Drilling of the seventh of the planned nine production wells at the Lineynoye oil field has now been completed ahead of schedule. Preliminary log and survey data indicate that the well encountered the thickest net pay to date in the development programme.

UK A reservoir engineering study on the West Firsby Field is now complete. The work undertaken on West Firsby has highlighted the potential for significant unswept oil. These additional reserves will be targeted by the next well.

The workover programme on Crosby Warren and West Firsby is now complete with WF6 remaining to come back onstream in the near future. An update on production will be provided in September along with a reserves update for West Firsby.

Following the production testing of the Hykeham-1 well, it is anticipated the well will be plugged and abandoned.

Tags: PetroNeft Resources plc




   

Add a Comment to this Article

Please be civil. Job and promotion will not be added into the comment page.

(Use Markdown for formatting.)

This question helps prevent spam:

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us

 

sitemap xml


 

Home