Production tubing has been installed in the Donnybrook Energy Bigstone Hz 15-32-60-22 W5M well (25% working interest to Pennant) and a 7 day production test has been completed.
Thomas Yingling, President of Pennant Energy Inc. provide an operations update on its Bigstone Montney high natural gas liquids resource play. The well flowed at an average rate of 1.1 mmcf of gas per day and 153bbls of fluid per day. The fluid was a combination of condensate and load oil from the hydraulic fracture treatment. To date the well has recovered 992 m3 of frac oil from the 1,810 m3 of load oil that was injected during the fracture operation. A review of the 24 stage hydraulic fracture that was performed on the well indicates that only 5 of the 24 stages of the planned fracture programed were successfully stimulated.
During the hydraulic fracture operation 460 tons of fracture propant and fluids were placed. A mechanical failure during the first stage of the hydraulic fracture program appears to have prevented up to 16 stages of the Montney formation from being fracture stimulated and 3 stages may have received all of the 360 tonnes of hydraulic fracture stimulation that was to planned for the first 18 stages.
Tags:
Pennant Energy Inc.
Add a Comment to this Article
Please be civil. Job and promotion will not be added into the comment page.