Otto Energy Limited, as operator of the producing Galoc oilfield joint venture offshore the Philippines, provides the following update on the Galoc-5H and Galoc-6H drilling campaign in SC14C, part of the Galoc Phase II development project approved in 2012.
Progress
During the period from 0600 hours (AWST) on 11 September 2013 to 0600 hours (AWST) on 18 September 2013, drilled the G-5H well 8½' hole horizontally to a final total depth of 4,497 metres and commenced running the completion liner and assembly.
This marks the successful conclusion of the major drilling activities of the Phase II project with remaining drilling rig based operations being for well completions and installation of subsea trees. The G-5H and G-6H wells have been drilled to a combined total of 3,177m through horizontal reservoir section within which a significant 1,645m of net oil pay has been encountered. Data recorded during drilling shows high reservoir permeability in both wells which suggests good production deliverability will be achieved. Well deliverability will be confirmed when the wells are flowed to surface in the coming weeks forthe well clean-up operations.
Tags:
Otto Energy Limited
Add a Comment to this Article
Please be civil. Job and promotion will not be added into the comment page.