Scandinavian Oil-Gas Magazinehttp://www.scandoil.com/moxie-bm2/news/oilex-completes-plug-milling-operations.shtmlOilex completes plug milling operationsOilex Ltd has completed plug milling operations. Cambay-77H started unaided controlled flowback with gas observed at surface while
[an error occurred while processing this directive]
Edit page New page Hide edit links Oilex Ltd has completed plug milling operations. Cambay-77H started unaided controlled flowback with gas observed at surface while successfully milling out 4 isolation plugs, including 1 that failed to seal properly. Since the previous update on 7 July 2014: The isolation plugs were successfully milled 8 fractures into the reservoir were connected to the well bore The well started to flowback unaided under controlled conditions during milling Gas flowed to surface during milling operations Production testing equipment was positioned and commissioned |