Scandinavian Oil-Gas Magazine

http://www.scandoil.com/moxie-bm2/news/oilex-announces-that-the-cambay-77h-site-construct.shtml

Oilex announces that the Cambay-77H site construction has been completed on schedule

Oilex Ltd is pleased to announce that the Cambay-77H site construction has been completed on schedule. All 149

[an error occurred while processing this directive]

Edit page New page Hide edit links

Oilex - Cambay field

Oilex Ltd is pleased to announce that the Cambay-77H site construction has been completed on schedule. All 149 packages of the LR-4 Rig components have been delivered and unloaded at site.

Due to the progress to date being within the scheduled timeframe, the proposed spud date of Cambay-77H remains unchanged to be between 22 February and 9 March 2014.

Managing Director of Oilex, Ron Miller, said,"We are very pleased with the progress at the Cambay-77H site. The safe and timely manner that the team has completed the civil works and delivery and unloading of all rig components allows us to remain on schedule."

Tags: Oilex Ltd