Northcote has completed the planned infrastructure upgrades at the Shoats Creek Field in Louisiana. Following the completion of the infrastructure upgrades, which have been inspected and approved by the State, the field is fully equipped to support production from the LM#20 well as well as production from future Frio wells up to an estimated capacity of 1,500 BOPD. The infrastructure work completed includes:
Installation of 5,400 barrel oil and water storage tanks with room for incremental additions as production grows in the course of drilling additional wells
Installation of high and low pressure separators, heating, flare stacks and other necessary production equipment
Installation of associated pump and pipeline work