Nido provides Seismic acquisition update


Published Nov 12, 2007
[an error occurred while processing this directive]

Edit page New page Hide edit links

Nido provides Seismic acquisition update

Nido Petroleum Limited provides an update on the progress of the company’s seismic acquisition campaign currently underway offshore NW Palawan basin, Philippines.

The seismic campaign, which is the largest in Nido's history, extends over SC 54, SC 58 and SC 63 comprising a combined total of 5,475 km of 2D and 826 sq km 3D seismic.

SC 54 (Nido operated): The CGGVeritas MV 'Pacific Titan' completed acquisition of 165 sq km of new 3D seismic on October 30, 2007. The survey was designed to provide greater coverage of the Late Miocene 'Pagasa' Turbidite play along the western flank of SC 54 and adjoins the Abukay 3D seismic survey acquired by the SC 54 Joint Venture in late 2006. Data processing is underway with the final 3D cube expected in Q1 2008.

SC 58 (Nido Operated): The CGGVeritas MV 'Pacific Titan' mobilized following the completion of the SC 54 Abukay 3D survey, commencing acquisition on November 1, 2007 of 661 sq km 3D and 2,350km 2D seismic, of which 450km will be acquired as line extensions into adjacent SC 54.

As of the 9th November the SC 58 survey was on schedule at 15% complete & is expected to be completed by the 14th January 2008, subject to weather.

SC 63 (PNOC-EC operated): The CGGVeritas MV 'Pacific Sword' suspended acquisition on November 5th due to damage to the trailing equipment. Acquisition of the remaining program is now scheduled to resume on November 18th following the completion of another operational license within the group shoot. The SC 63 3,125km of new 2D seismic will provide a uniform 'base-line' survey of modern 2D seismic data across the entire block. A 2 x 2 km infill seismic grid will be acquired over the Aboabo-1 well in the southern sector of the block which is reported to have flowed gas at 50MMscf/d.

As of November 9th the SC 63 survey was 63% complete and is expected to be completed by the 30th November 2007, subject to weather

Tags: Nido Petroleum Limited




   

Add a Comment to this Article

Please be civil. Job and promotion will not be added into the comment page.

(Use Markdown for formatting.)

This question helps prevent spam:

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us

 

sitemap xml


 

Home