Solo Oil advises that the Horse Hill-1 well has now been drilled to the third casing point at 6,612 feet measured depth (MD), and will now be electrically logged through the observed Jurassic reservoir sections. Electronic logging and full interpretation of these logs is expected to take approximately one week.
The depth of the third casing point was deepened from the previously prognosed at 5,900 feet to a depth of 6,612 feet MD due to a number of reservoir intervals being identified deeper and thicker than expected.
On completion of the detailed logging, it is planned that a 9 5/8-inch casing will be set prior to drilling in an 8 ½-inch hole to a total depth (TD) of approximately 8,680 feet MD in order to test for deeper Triassic aged formations where further electric logs will be acquired.