Hansa Hydrocarbons provides an operational update on its Juliet field development


Published Jul 17, 2013
[an error occurred while processing this directive]

Edit page New page Hide edit links

Hansa Hydrocarbons Limited

Hansa Hydrocarbons Limited (Hansa) is pleased to announce certain significant developments towards first production from the Juliet field.

The first of two horizontal subsea production wells was successfully drilled and completed in the first half of 2013 with the Noble Ronald Hoope drilling rig. Upon clean-up the well flowed at stabilized rate of 63 million standard cubic feet per day, being limited by the capacity of the test separator.

The well is now suspended and will be hooked-up for production following installation of the subsea pipelines and facilities and completion of topsides works at Pickerill A platform later this year. The second well is planned to be drilled in Q4 2013.

Tags: Hansa Hydrocarbons




Advertisment:

Add a Comment to this Article

Please be civil. Job and promotion will not be added into the comment page.

(Use Markdown for formatting.)

This question helps prevent spam:

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us
Stats

 

sitemap xml