Global Maritime Completes Njord A Disconnection and Tow to Shore


Published Sep 1, 2016
[an error occurred while processing this directive]

Edit page New page Hide edit links

Global Maritime logo-2

Global Maritime Consultancy & Engineering, a provider of marine warranty, dynamic positioning and engineering services to the offshore sector, has successfully led the disconnection and towing operations of the Njord A semi-submersible floating production platform from the Njord field. The Njord A platform arrived safely in Klosterfjorden on the August 23rd, where a handover to Kværner was achieved.

The 346 nautical-mile journey was carried out by Global Maritime, on behalf of the operator Statoil. The news follows the successful towing of the oil storage and offloading vessel Njord B by Global Maritime to Sterkoder, Kristiansund earlier this summer.

Global Maritime was responsible for the project management, engineering, design, fabrication and procurement of equipment, as well as all offshore management activities for the Njord A and Njord B mooring disconnection and tow.

Global Maritime’s responsibilities included the disconnection of 12 mooring lines, the recovery of one complete mooring line (excluding the suction anchor) for onshore inspection and the towing-in of the Njord A platform to Klosterfjorden outside the Stord yard. Statoil coordinated the decommissioning activities including the disconnection of risers and the temporary plugging of wells.

Global Maritime worked closely with Statoil’s Njord Future Marine Project and Operations Vessel and Rigmove that provided the vessels and rig positioning services for the offshore operations.

David Sutton, CEO of Global Maritime Consultancy & Engineering, continues, “With a project of such complexity and with the subsea infrastructure still in tact, it was crucial that mooring disconnection activities and the towing of the platform took place with maximum precision and care. This is what Global Maritime achieved with the platform being disconnected from its moorings, departing the field, and arriving in Stord ahead of schedule. We look forward to working with Statoil on future similar projects.”

Tags: Global Maritime Consultancy & Engineering




Advertisment:

Comments on this page are closed.

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us
Stats

 

sitemap xml