Gas2Grid provides update on drilling-workover progress


Published Jan 9, 2013
[an error occurred while processing this directive]

Edit page New page Hide edit links

Gas2Grid

As of Midnight, Monday, 8th January, 2013 (Sydney DST) electric logging operations had been completed over the open hole section in Gumamela-1. No significant porosity or reservoir development is evident in either the Cebu Limestone or the underlying Oligocene age clastic sediments.

The well has been drilled to a depth of 1,051.6 metres KB (3,450 feet KB) to within a dominantly claystone and siltstone with minor sandstone Oligocene age formation immediately below the Cebu Limestone. It has been decided to plug and abandon Gumamela-1. The current operation is preparing to set cement plugs.

MALOLOS-1: The Company is now focused on completing the workover and testing of Malolos-1, which it plans to complete over the next 4-6 weeks. Rig-1 is conducting this work and operational updates will be provided by ASX release when relevant information becomes available.

Tags: Gas2Grid




Advertisment:

Add a Comment to this Article

Please be civil. Job and promotion will not be added into the comment page.

(Use Markdown for formatting.)

This question helps prevent spam:

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us
Stats

 

sitemap xml