First Claire Ridge topside modules safely installed West of Shetland


Published Jun 26, 2015
[an error occurred while processing this directive]

Edit page New page Hide edit links

BP – Clair Ridge Platforms

BP and its co-venturers, ConocoPhillips, Chevron and Shell, are pleased to confirm the safe installation of the new Clair Ridge platform’s quarters and utilities (QU) topside modules, a major milestone in the Clair Ridge project.

The QU platform comprises three modules – the quarters and utilities integrated deck (QUID) which has a lift weight of 9,400te; the power generation (GM) module which has a lift weight of 4,550te; and the living quarters (LQ) module which has a lift weight of 2,210te. They were safely lifted onto the pre-installed jackets by the Heerema Thialf heavy lift vessel.

The hook up and commissioning of these modules has created over 600 jobs, including six electrical apprentices, all of which have recently been recruited through Amec Foster Wheeler.

Clair Ridge is a multi-billion investment in the second phase of development on the Clair field which lies 75km to the west of the Shetland Islands. The project comprises two new bridge-linked platforms and new pipeline infrastructure to connect storage and redelivery facilities on Shetland. The next major milestone will be the installation of the production and drilling (DP) platform topside modules, scheduled for summer 2016, with production expected to commence in late 2017.

Tags: BP PLC, Chevron Corporation




Advertisment:

Comments on this page are closed.

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us
Stats

 

sitemap xml