Europa Oil & Gas (Holdings) provides an update on production operations in the East Midlands. The workover on West Firsby-6 is now complete and the well is back on jet pumped production. It may take a short time for reservoir drawdown, and thus production, to reach a stable maximum. All 5 of Europa's production wells are onstream.
A key element of the company's continuing revenue growth strategy is the drilling of a new production well on West Firsby which, as previously announced, is planned to commence in December.
Paul Barrett, Managing Director, said, "It is very satisfying to have all our production wells back onstream and we can now concentrate on delivering a new production well on West Firsby in the next two months or so. We expect to see further significant production growth in early 2011."