Scandoil.com

Europa Oil & Gas provides operational update


Published Sep 3, 2007
[an error occurred while processing this directive]

Edit page New page Hide edit links

Europa Oil & Gas (Holdings) PLC - Egypt License Award-Spotlight

The Directors of Europa Oil & Gas (Holdings) plc announces that the second sidetrack of the Costisa-2 well, Costisa-2Y, has reached final total depth of 1,155 metres and has now been cased. The well, situated in the EPI-3 concession in the Romanian Carpathians, recorded strong gas shows of up to 58% in the primary target and is being prepared for testing.

The target Burdigalian Sandstones were encountered between 1,083 and 1,110 metres measured depth and exhibited strong drilling gas readings throughout. Additional thinner sandstones with gas shows were encountered above the main sand. A 2-3 week testing programme is scheduled to commence this week.

The top of the main sandstone is approximately 10 metres higher in true vertical depth than in the Costisa-1 well. Hole problems were encountered throughout the drilling of this well, leading to two sidetracks. However, as the majority of the well operations were undertaken under a fixed price turnkey contract, the cost implication for these delays was minimised.

The EPI-3 concession has been divided such that Europa's working interest in the eastern Costisa area (EPI-3 East) is 80% and Moravske naftove doly's (MND's) interest is 20%. Under the terms of a farm-in agreement, Aurelian Oil & Gas plc is funding 60% of Europa's 80% to earn up to 27.4% working interest and being granted an option to operate any development in EPI-3 East, subject to any necessary consents. As a result, if Aurelian fully exercises its option under this agreement, the subsequent working interest split will be Europa 52.6%, Aurelian 27.4% and MND 20%.

In the Romanian Cuejdiu Block EIII-3, some 50km north of Costisa, the Boistea-1 well spudded on the 29th August. This well is targeting a Sarmatian gas prospect with multiple targets and is anticipated to take around 35 days to drill to a programmed total depth of 2,400 metres.

Paul Barrett Managing director of Europa, said, 'The strategy of a turnkey contract for Costisa-2 was a good decision which has protected the partnership from the majority of cost overruns associated with the drilling phase. The very strong drilling gas readings in this confirmation well are highly encouraging. As we move into the testing phase we hope to be able to report positive results within a month.'

Europa Oil & Gas (Holdings) plc announces that the second sidetrack of the Costisa-2 well, Costisa-2Y, has reached final total depth of 1,155 metres and has now been cased. The well, situated in the EPI-3 concession in the Romanian in the primary target and is being prepared for testing.

The target Burdigalian Sandstones were encountered between 1,083 and 1,110 metres measured depth and exhibited strong drilling gas readings throughout. Additional thinner sandstones with gas shows were encountered above the main sand. A 2-3 week testing programme is scheduled to commence this week.

The top of the main sandstone is approximately 10 metres higher in true vertical depth than in the Costisa-1 well. Hole problems were encountered throughout the drilling of this well, leading to two sidetracks. However, as the majority of the well operations were undertaken under a fixed price turnkey contract, the cost implication for these delays was minimised.

The EPI-3 concession has been divided such that Europa's working interest in the eastern Costisa area (EPI-3 East) is 80% and Moravske naftove doly's (MND's) interest is 20%. Under the terms of a farm-in agreement, Aurelian Oil & Gas plc is funding 60% of Europa's 80% to earn up to 27.4% working interest and being granted an option to operate any development in EPI-3 East, subject to any necessary consents. As a result, if Aurelian fully exercises its option under this agreement, the subsequent working interest split will be Europa 52.6%, Aurelian 27.4% and MND 20%.

In the Romanian Cuejdiu Block EIII-3, some 50km north of Costisa, the Boistea-1 well spudded on the 29th August. This well is targeting a Sarmatian gas prospect with multiple targets and is anticipated to take around 35 days to drill to a programmed total depth of 2,400 metres.

Paul Barrett Managing director of Europa, said, 'The strategy of a turnkey contract for Costisa-2 was a good decision which has protected the partnership from the majority of cost overruns associated with the drilling phase. The very strong drilling gas readings in this confirmation well are highly encouraging. As we move into the testing phase we hope to be able to report positive results within a month.'




   

Add a Comment to this Article

Please be civil. Job and promotion will not be added into the comment page.

(Use Markdown for formatting.)

This question helps prevent spam:

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us

 

sitemap xml


 

Home