Scandoil.com

Emerald Energy updates Syria, block 26 operations


Published Sep 10, 2009
[an error occurred while processing this directive]

Edit page New page Hide edit links

Emerald Energy provides Syria operations update-Spotlight

Emerald Energy provides the following update on operations in Block 26, Syria.

Khurbet East Field Oil Production

Cumulative gross oil production from the Khurbet East field has recently reached 4 million barrels, with minimal water production to date.

Khurbet East No.12 Delineation Well

Drilling operations have been completed at Khurbet East No.12, a vertical delineation well located approximately 3.2 kilometres south of the Khurbet East No.8 vertical well, previously the most southerly well drilled in the field.

Khurbet East No.12 was drilled to a total measured depth of 2,070 metres, encountering the top of the Cretaceous Massive reservoir at a measured depth of 1,984 metres, equivalent to 1,592 metres true vertical depth subsea (TVDSS) and 22 metres deeper than the 1,570 metres TVDSS level interpreted as the best estimate of the oil-water contact for the purpose of determining reserves.

Shows of viscous oil were recorded while drilling through the reservoir and approximately 6 metres of core was recovered near the top of the reservoir. Preliminary analysis of core and wire-line logs indicates approximately 10 metres of net reservoir, extending down to 1,605 metres TVDSS, with an average porosity of 18%. The reservoir parameters and oil quality appear similar to those encountered in Khurbet East No.8 but the average oil saturation is interpreted to be significantly less in the Khurbet East No.12 well. The lower oil saturation levels seen in this well may be due to an extended transition zone or to oil remaining from migration into the field.

A wire-line formation pressure and fluid sampler measured formation pressures at depths of approximately 1,992 metres (1,600 metres TVDSS) that are interpreted to be consistent with the oil pressure gradient previously observed in the Khurbet East field. However, three fluid samples recovered by this wire-line tool from the same depth contained formation water. Flow testing operations are planned to be conducted at Khurbet East No.12, following demobilisation of the drilling rig from the well location, to determine the fluids that will be produced under production conditions.

Khurbet East No.11 Flow Testing

Initial flow testing of the Khurbet East No.11 horizontal development well over a one week period has been completed. The 60 metre horizontal section in Khurbet East No.11 well penetrates the top of the Cretaceous Massive reservoir at approximately 1,540 metres TVDSS and ends at approximately 1,562 metres TVDSS.

The well flowed oil of approximately 25 degrees API at an average rate over a 44 hour period of approximately 1,660 barrels per day, under natural flow and through a 48/64” choke, with a water cut of approximately 30%.

Further production monitoring operations are planned to be conducted to determine the source of the water production and a remedial water shut-off operation may be undertaken which may allow production from this well to be received at the Early Production Facility.

Yousefieh No.1 Remedial Cementing and Flow Testing

The Yousefieh No.1 well, drilled in November 2008, was re-entered in August 2009 to conduct remedial cementing operations on the production liner and to subsequently flow test the well.

Remedial cementing operations were conducted successfully and the production liner was then perforated across a 14.5 metre interval between 1942.5 metres and 1957 metres. During subsequent flow testing operations the well flowed oil of approximately 25 degrees API to surface at an average rate of approximately 356 barrels per day over a 7 hour period, under natural flow and through a 48/64 inch choke, with an average water cut of less than 1%. Under artificial lift with nitrogen and through a 2 inch choke, the well flowed over a 2 hour period at an average oil rate of approximately 824 barrels per day with a water cut of less than 1%.

Yousefieh No.1 is now being completed for future production.

Yousefieh No.2 Flow Testing

The Yousefieh No.2 well, drilled in February 2009, was re-entered in August 2009 to evaluate the flow potential of the interval between 1,978 and 1,991 metres which, based on wire-line logging information, was interpreted to contain oil but had previously not flowed to surface.

Using a work-over rig, a production liner was set over the open-hole section and an acid stimulation was conducted across the potential reservoir interval.

Following the acid stimulation operation, the well flowed 17 degrees API oil to surface at an average rate of 139 barrels per day over a 12 hour period, under artificial lift using nitrogen and through a 2 inch choke, with a water cut of 49%.

Yousefieh No.3 Appraisal Well

Following demobilisation from the Khurbet East No.12 well location, the drilling rig will move to commence drilling operations on the Yousefieh No.3 appraisal well, located approximately 500 metres to the south-east of the Yousefieh No.1 discovery well. The Yousefieh No.3 well is planned to take approximately 45 days to drill and evaluate.

Emerald’s Chief Executive Officer, Angus MacAskill, said,“We are very pleased with the production performance experienced in the Khurbet East field and the continued progress with the delineation and appraisal of Khurbet East and Yousefieh fields. We look forward to the results of flow testing at the Khurbet East No.12 well and the results of the upcoming Yousefieh No.3 appraisal well.”

Tags: Emerald Energy Plc




   

Add a Comment to this Article

Please be civil. Job and promotion will not be added into the comment page.

(Use Markdown for formatting.)

This question helps prevent spam:

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us

 

sitemap xml


 

Home