Total reports the start-up of the Itaú gas and condensate field located on Block XX (Tarija Oeste) 400 kilometres south of the city of Santa Cruz in the Andean Cordilleras foothills.
The first phase of the development came on stream on February 2nd and is designed to produce 1.5 million cubic meters of gas per day (10,000 barrels of oil equivalent per day (boe/d)), which will be processed in the facilities of the neighboring San Alberto field. Itaú gas production will mainly be exported.
The Block XX joint venture has also submitted for approval to YPFB a development plan which aims at increasing Itaú's production from 1.5 to 5 million cubic metres per day by mid-2013 (about 35,000 boe/d).
Total E&P Bolivie discovered the Itaú field in 1999. After having first conducted delineation operations between 2001 and 2003 and then supervised the first development phase of the field, Total E&P Bolivie sold on February 1st a participating interest on Block XX of 4% to YPFB Chaco and of 30% to Petrobras, to which was also transferred the operatorship. After completion of these transactions, Total E&P Bolivie will hold a 41% interest on Block XX.
Tags:
Total
Add a Comment to this Article
Please be civil. Job and promotion will not be added into the comment page.