Scandoil.com

Delta Petroleum provides update on Paradox Basin


Published Dec 14, 2007
[an error occurred while processing this directive]

Edit page New page Hide edit links

Delta Petroleum provides update on operating activities

Delta Petroleum Corporation provided the following update regarding its production, drilling and other operating activities.

OPERATIONS UPDATE

Greentown Project, Paradox Basin, UT, 70% WI – The Company has drilled the Federal 28-11 to a depth of 9,472 feet, which was reached on November 19, 2007. At that time, the well began flowing and flaring natural gas at bottom hole pressures of approximately 8,000 psi from the lowest interval referred to as the “O” zone. The “O” zone is the same clastic interval that caused the surface blow out in the Company’s Greentown State 36-11 discovery well. The pressures experienced in this interval are very consistent with pressures seen in both the Greentown State 36-11 and 32-42 wells, which are 6 miles to the north and l.5 miles to the south, respectively.

For approximately two weeks the well flowed at rates and pressures that made it challenging to run production casing, which has now been accomplished. The Federal 28-11 well has encountered the same sequence of alternating clastic intervals and interbedded salt sections as found in the Company’s two previously drilled Greentown project wells. The results from the Federal 28-11 thus far, in conjunction with the initial results from the Greentown State 36-11 and Greentown State 32-42, provide the Company ample evidence to believe in the economic viability and immense reserve potential of the Greentown Field. Within an 11 township area surrounding the Greentown Project, 38 wells have now been drilled that penetrated at least some of the Paradox Salt section. Based on this control, the Paradox Formation can be characterized as consistent and continuous over a large area.

The Company is also drilling the Greentown Federal 36-24 which is located three-quarters of a mile south of the previously referenced 36-11 discovery well, and 1.5 miles southeast of the Federal 35-12 well. The 35-12 well was temporarily abandoned this summer due to excessive over-pressuring in the upper interval at approximately 5,700 feet in depth. The Federal 36-24, which has drilled through the same upper over-pressured intervals that were evident in the Federal 35-12, did not encounter any excessive over-pressuring and appears to be hydrocarbon-bearing in all clastic intervals encountered thus far based on mud log shows. Information from the other 37 wells drilled in the immediate area also did not encounter this degree of over-pressuring, further substantiating our belief that the excessive over-pressuring experienced in the Federal 35-12 was anomalous and localized.

With regard to the Greentown pipeline project, the National Environmental Protection Act (NEPA) work has been completed, and the environmental assessment has been submitted to the Bureau of Land Management. The Company believes that new well permits and the pipeline permitting process will move forward in an expeditious manner. Pipeline construction and initial operations should occur by the end of the second quarter of 2008.

The Company expects to report additional results from the Paradox Basin in the near future and will continue to drill with two rigs in the Greentown project.

Central Utah Hingeline Project, UT, 65% WI – The Federal 23-44 well has drilled the Navajo Formation on the Company’s Parowan Prospect. The Navajo exhibited good porosity and permeability, but resistivity logs indicate that the Navajo Sandstone appears to be water-bearing. The Company has set intermediate casing and is currently drilling its second primary objective, the Kaibab Formation. The Kaibab Formation is productive in the Upper Valley Field, which has produced 27 million barrels of oil from 25 wells and is located approximately 67 miles to the east. The nearest well to the Parowan Prospect that penetrated the Kaibab Formation was drilled by another operator 16 miles to the southwest and had both mud log and sample oil shows. To date, drilling information from the Federal 23-44 is consistent with the geophysical interpretation that identified a large structure. The well is expected to reach total depth by the end of December.

Vega Unit and North Vega, Piceance Basin, CO, Avg. 50 – 100% WI – The Company continues to develop the Vega Unit area with four rigs and should have 67 wells producing and 24 wells drilled and waiting on completion by year end, at which time the productive capacity of Vega area wells should exceed 40 million cubic feet (Mmcf) of natural gas per day. Additional pipeline capacity should be available by the end of the first quarter in 2008, when production rates should increase accordingly.

Tags: Delta Petroleum Corporation




   

Add a Comment to this Article

Please be civil. Job and promotion will not be added into the comment page.

(Use Markdown for formatting.)

This question helps prevent spam:

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us

 

sitemap xml


 

Home