Aker Solutions has been awarded contracts from Statoil to provide subsea production systems and services for the Troll Phase 3 and Askeladd natural-gas developments offshore Norway (photo: Aker Solutions)
Aker Solutions has been awarded contracts from Statoil to provide subsea production systems and services for the Troll Phase 3 and Askeladd natural-gas developments offshore Norway.
The company will deliver a subsea production system consisting of two manifolds and nine trees for the Troll development in the North Sea. The system for Askeladd in the Barents Sea will be comprised of two manifolds and four trees. Both orders include installation and commissioning support services.
The contracts have a total estimated value of between NOK 1.5-2 billion kroner and will be booked in the first quarter. Work starts this month, with final deliveries scheduled for 2020.
“We look forward to working with Statoil on these fields, which are key to further developing Norway as a major gas supplier,” says Aker Solutions Chief Executive Officer Luis Araujo. “We expect to generate significant synergies by building on our work on another major ongoing Statoil project, the delivery of the subsea production system for the Johan Castberg field in the Barents Sea.”
Work on the two systems will involve facilities in Norway, Brazil, the UK and Malaysia. Initial deliveries are scheduled for the second quarter of 2019. Aker Solutions’ facilities in Ågotnes on the west coast of Norway and Hammerfest, located on the country’s northern tip, will provide the subsea services for Troll and Askeladd.
Troll, which contains about 40% of Norway’s offshore gas reserves, is expected to continue producing for decades to come. Askeladd is slated to come on stream after 2020, helping to further develop Norway’s newest oil and gas region in the far North. It is located about 180 kilometres from the Melkøya onshore plant, where the gas will be processed.
Tags:
Aker Solutions,
Statoil
Comments on this page are closed.