Candax provides operational update on Tunisian drilling

Candax Energy Inc. drilled the first well in the three well development program on the El Bibane oil and gas field, EBB-4, to a total depth of 2,298 meters on October 3rd and logging was completed on October 4th.

The oil/water and the gas/oil contacts in the vertical section of the well are as expected, providing a gross oil column of 25 to 30 metres, and the reservoir quality in the Zeebag dolomite is better than expected. Operations are continuing with the drilling of the 500 metre horizontal production section of the EBB-4 well and upon completion, the production platform will be installed and tied into the oil and gas pipelines.

The tie-in will take approximately two weeks and production will then begin to the central processing facility onshore. First production is anticipated to commence in November.

Michael Wood, President and CEO, commented, "We are very pleased that the results from the EBB4 well comfortably underpin our base case 2P oil and gas reserves for El Bibane. We are fully focused on getting first production on stream and completing the field development program for El Bibane as soon as possible. In addition, planning for the onshore drilling campaign on our Chaal and Ezzaouia projects is progressing well for early 2008, and further announcements on these programs will be made in due course."




   

Add a Comment to this Article

Please be civil. Job and promotion will not be added into the comment page.

(Use Markdown for formatting.)

This question helps prevent spam:

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us

 

sitemap xml


 

Home