BPZ Energy provides Block Z-1 operations update


Published Mar 4, 2013
[an error occurred while processing this directive]

Edit page New page Hide edit links

BPZ Energy reports completion of CX11-16X Corvina well-Spotlight

BPZ Energy provided an update to Block Z-1 operations as well as year-end 2012 oil reserves.

Corvina CX-15 Drilling

Preparations for the new CX-15 development drilling campaign continue with some delays deemed necessary to make adjustments to the platform's draft (submerged depth). As a result, the first well spud is expected to occur within three to six weeks, depending on progress, as well as weather and sea conditions. Targeted depth of the first CX-15 well, named 4D, will be approximately 6,700 feet subsea. Conventional cores of the reservoir rocks will also be cut during drilling operations.

Corvina CX-11 Workovers

The workover campaign at the CX-11 platform has resumed with work currently underway at the 14D well, which will be followed by a workover on the 15D well. Other CX-11 wells are under review for potential workovers during 2013.

Tags: BPZ Energy




Advertisment:

Add a Comment to this Article

Please be civil. Job and promotion will not be added into the comment page.

(Use Markdown for formatting.)

This question helps prevent spam:

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us
Stats

 

sitemap xml