BJ Process and Pipeline Services (BJ PPS) has successfully completed a pipeline pre-commissioning operation for Subtec Middle East Limited, a subsidiary of Global Industries Ltd. Subtec is the installation contractor for the offshore section of the Atlantis development in the United Arab Emirates.
Atlantis comprises a wellhead platform that feeds a stand-alone pipeline extending 75km to the shore. Natural gas produced from this development will provide energy in the United Arab Emirates.
Prior to start-up and commissioning, BJ PPS provided pre-commissioning services, including flooding, dewatering, hydrotesting, air-drying and nitrogen purging to –20°C on the 75km x 14-inch pipeline, which extends from the Atlantis platform to the onshore first flange on the beach before the RAK gas terminal. The work was performed by engineers and technical personnel with specialised equipment based in Dubai.
“We are very pleased the pre-commissioning operation for Subtec on the Atlantis Project was carried out safely and efficiently,” said Lindsay Link, general manager of BJ Process and Pipeline Services “The entire operation was completed in just 26 days. This is extremely impressive considering the 75km length of the pipeline. We look forward to working again on behalf Subtec in the future,” he added.
Tags:
BJ Process and Pipeline Services,
Subtec Middle East Limited
Add a Comment to this Article
Please be civil. Job and promotion will not be added into the comment page.