Bankers Petroleum Ltd. provides the following operational update:

Production and Oil Price

Oil sales from the Patos-Marinza oilfield in Albania during the second quarter averaged 12,152 bopd compared to first quarter sales of 11,894 bopd. The last export shipment of approximately 54,000 barrels (equivalent to ~600 bopd for the quarter) scheduled for June 29th was delayed due to late vessel arrival to July 2nd and will be included in the next quarter oil sales. Oil inventory on June 30th was 239,000 barrels, an increase of 71,000 barrels in the quarter (equivalent to ~800 bopd) from the March 31st inventory level of 168,000 barrels, as a result of additional new well site tanks and storage tanks at the export terminal requiring certain minimum operational volumes in each tank.

Average production for the second quarter was 12,973 bopd representing a 7% increase from 12,147 bopd in the first quarter, yet approximately 1,200 bopd lower than forecast due to several operational challenges detailed below. Current production is 13,150 bopd.

The Patos-Marinza oilfield currently has shut-in production of 1,750 bopd. This volume is approximately 60% higher than normal, representing 1,000 bopd of additional productive capacity. Most of these wells are waiting on service rigs for workovers, a few are shut-in for proximity to new drilling and the remainder are wells with high water production shut-in to provide water disposal capacity for water from high productivity oil wells. To mitigate these challenges, additional service rigs are being sourced and new water disposal wells are being equipped to handle additional water disposal volumes from the field.

The Patos-Marinza second quarter average oil price was US$77.02 per barrel (representing 66% of the Brent oil price of US$117.36 per barrel) an increase of 13% compared to the first quarter's average oil price of US$68.06 per barrel (65% of Brent). With the current differential between Brent and WTI, Patos-Marinza crude is presently priced at approximately 80% of WTI.

Drilling Update

Nineteen (19) wells have been drilled during the second quarter, eighteen (18) horizontal production wells and one (1) vertical water disposal well. Fifteen (15) of these wells have been completed and are on production with three (3) awaiting completion including the third Gorani horizontal well test, the first two of which are currently producing at rates of 170 and 180 bopd. The success of these two wells has now validated primary productivity from the Gorani formation in the northern area of the field and the Company intends to further develop this formation with the addition of a large number of horizontal wells to access more than 220 million barrels of oil in place assigned to the Gorani formation in this part of the field.

Production rates from fifteen (15) horizontal wells drilled and put on production in the second quarter are averaging 180 bopd with strong initial production in the lower Gorani sands tested and continuing in the Driza (D1) sands. Production rates from the sixteen (16) horizontal wells drilled in the first quarter are averaging 135 bopd and the average production from all seventy-five (75) producing horizontal wells in the field is 120 bopd per well at the end of the second quarter.

Horizontal well decline analysis is continuing with current indication showing varied decline rates depending on formation, area of the field, and well optimization with current average declines of approximately 25% per year. High initial productivity wells are exhibiting 30 to 50% declines in the first six to twelve months followed by a leveling off in rate and reduced declines of 10 to 20% beyond the initial decline period.

The fourth drilling rig arrived in Albania in May and after start-up delays, the rig spud its first well on June 5th and is currently drilling its second well at the Patos-Marinza oilfield; this delay had a negative impact on the second quarter production numbers. The fifth drilling rig has now been contracted and is expected to be ready for drilling operations in October 2011. The Company's current estimates are to drill 79 horizontal wells and complete 82 well reactivations in 2011.

Due to observed variance in productivity and decline rates of the horizontal wells versus forecast rates as well as the loss of some productivity from old vertical wells due to casing conditions of these wells, the Company is providing guidance that exit production in 2011 will now range from a high case of 20,000 bopd, likely case of 18,000, and a low case of 16,000 bopd.

Well Reactivations

Reactivation and recompletion work continued in the second quarter with fourteen (14) wells reactivated, nine (9) of which are on production and averaging 33 bopd per well. Current production from these wells is 300 bopd. Production from nine (9) wells reactivated in the first quarter and on production is currently 230 bopd averaging 26 bopd per well.

The current production split is 7,470 bopd (representing 57%) from new horizontal wells and 5,630 bopd from reactivated vertical wells.

Thermal Program & Exploration Block "F"

Road access and site construction for the thermal facilities have been completed. Drilling the vertical delineation well is scheduled for later this month to be followed immediately with two (2) thermal horizontal wells. The first 60-day steam injection cycle is scheduled for September 2011.

Seismic reprocessing and interpretation on Block "F" is progressing to finalize the location for drilling the first gas exploration well in the fourth quarter.

Infrastructure Development

Construction on the first phase of the crude oil sales pipeline, which connects the Patos-Marinza oilfield to the storage and loading Hub facility at Fier, is progressing and the project is scheduled for September 2011 completion. Social and environmental impact assessments for the second phase of the pipeline, from Fier to the export terminal at Vlore, are underway.

Construction of the third and fourth oil treating train expansions of the Central Treatment Facility (CTF) are underway and on schedule for completion during the fourth quarter of 2011 and will increase the CTF capacity to 25,000 bopd.

Construction of the Seman River bridge in the northern area of the Patos-Marinza oilfield is progressing with completion expected in December 2011, which will facilitate a larger drilling and reactivation program in the higher productivity area north of the river.

Kuçova

Water injection in one vertical well started in May 2011 and pressure and fluid level observations are being monitored in two vertical wells. With positive pressure build-up, the Company can expand the waterflood project and initiate production operations in 2012.

Environmental Initiatives

The pilot remediation project in Sector 3 is moving ahead with continuing strong results with the mechanical (centrifuge) separation unit providing the best outcome in cleaning contaminated solids and residues from contaminated sites. The bio-remediation test process is also continuing yet due to the nature of this type of treatment, will take a longer period to provide results.

Tags: Bankers Petroleum Ltd.




Advertisment:

Add a Comment to this Article

Please be civil. Job and promotion will not be added into the comment page.

(Use Markdown for formatting.)

This question helps prevent spam:

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us

 

sitemap xml