Northern Petroleum provides the following production update on the three wells in north west Alberta, Canada. As announced on 3 April 2014, all the wells were successfully drilled and completed as planned and operations then moved to a production testing phase.
Highlights
§ Production results support the development of the Keg River play as part of the low risk production led growth strategy
§ 13-33 and 14-22 both currently producing at a combined test rate of 280 bbls/d
§ 16-19 initially produced as expected; a cemented liner now needs to be run to replace the inflatable packer and isolate the water aquifer below the oil column
§ Production being trucked and sold locally at a sales price of approximately Cdn$96 per barrel
§ Short and medium term development of the play underway with three new wells planned in the summer