Karoon Gas Australia completes Kangaroo-2 down-dip side-track drilling Jan 29, 2015Karoon Gas Australia Ltd's Kangaroo-2 appraisal well, located in exploration Block S-M-1165, confirmed a 250 metre
Kangaroo 2 wireline logging complete Dec 4, 2014As at 2000 hrs BRST on 2 December 2014, wireline logging of the Kangaroo-2 appraisal well was complete and preparations were underway to
Kangaroo-2 appraisal well encounters five separate oil zones Nov 28, 2014As at 2000 hrs BRST on 25 November 2014 drilling had been completed at a total depth of 2,369 metres below rotary table (mRT) and a wireline
Kangaroo 2 appraisal well hits gas and oil Nov 21, 2014As at 2000 hrs BRST on 18 November 2014 drilling is ongoing in the 12-1/4' hole section at a current depth of 1,760 mRT.
Karoon Gas spuds Kangaroo-2 appraisal well Nov 7, 2014Karoon Gas Australia announce the spudding of the Kangaroo-2 appraisal well at 2135 hrs BRST on 5 November 2014. The top of the reservoir section is expected to be
Karoon takes possession of the Olinda Star drilling rig Oct 28, 2014Karoon Gas Australia has now taken possession of the Olinda Star Semi-submersible drilling rig from Petrobras. The rig is currently in the Campos Basin and expected to
Karoon Gas strikes gas in Browse Basin Jul 18, 2014Karoon Gas says that as at 0600 WST on 16th July 2014 wireline logging of the Pharos-1 borehole was ongoing. Since the last update,
Karoon Gas Australia provides update on Poseidon North-1 Exploration well May 19, 2014Since the 17 April 2014 Poseidon North-1 Progress Report, 9-5/8' casing was run and cemented at 3,820 mRT. The 8-1/2' hole was
Karoon Gas announces prospective resource volumes for Australia and Peru assets May 2, 2014Karoon is pleased to announce the results of independent reports completed by DeGolyer and MacNaughton
Karoon Gas announces Grace-1 reached total vertical depth at 5069mRT Jan 31, 2014At 0000 WDT on 26 January 2014, Grace-1 reached total vertical depth at 5069mRT. A zone of interest was encountered in
Karoon Gas provides update on Grace-1 exploration well in WA-314-P Jan 21, 2014As at 0600 WDT on 20 January, Grace-1 was drilling ahead at 4,844 metres in the 6-1/2" hole section. The current hole section is