Cue Energy provides Naga Utara-2 progress report Dec 27, 2013Cue Energy Resources Ltd (Cue) advises that at 08:00 local time on 20 December 2013, the Naga Utara-2 ST well is at a depth of 5,520 ft MDKB (1,676m).
Cue Energy provides Manaia-2/2A progress report Nov 19, 2013Cue Energy Resources Ltd (Cue) advises that at 0600 hours local time on 15 November 2013 the operator was setting plugs and abandoning
Cue Energy Resources provides Manaia-2 progress report # 7 Oct 21, 2013Cue Energy Resources Ltd (Cue) advises that the Manaia-2 well is at a depth of 2005m MDRT at 0600 hours local time on 18 October 2013. Current operations are preparing
Cue Energy provides Manaia-2 progress report # 1 Oct 14, 2013Cue Energy Resources Ltd advises that the Manaia-2 well is at a depth of 189m MDRT at 0600 hours local time on 6 September 2013.
Cue Energy Resources provides Manaia-2 progress report # 4 Sep 30, 2013Cue Energy Resources Ltd (Cue) advises that the Manaia-2 well is at a depth of 754m MDRT at 0600 hours local time on 27 September 2013.